Projects Archive

  • Work Performed

    Colman Dock is WSF’s largest and busiest ferry terminal supporting transportation across Puget Sound between downtown Seattle and communities in […]


    • Location: Seattle, WA
    • Contract: >$50M
    • Dates: 2017 - 2023

    Full Description

    SR519 Seattle Multimodal Terminal at Colman Dock

    Seattle, WA

  • Work Performed

    Removal of four undersized ship-to-shore (STS) container cranes from T18 and T46 in the North Harbor. On-site disassembly was performed […]


    • Location: Seattle, WA
    • Contract: < $3M
    • Dates: Dec-2018 - Apr-2019

    Full Description

    Terminal 18 & 46 Removal of Ship-to-Shore Container Cranes

    Seattle, WA

  • Work Performed

    Demolition and reconstruction of existing timber trestle Pier 62 and a portion of Pier 63, including, utility, roadway, and surface […]


    • Location: Seattle, WA
    • Contract: $20-50M

    Full Description

    Pier 62/63 Rebuild Phase 1 – Habitat and Alaskan Way Improvements

    Seattle, WA

  • Work Performed

    The Swan Lake Hydroelectric Project is a 22 MW hydroelectric facility with a concrete thin arch dam, intake, tunnel, penstock […]


    • Location: Ketchikan, AK
    • Contract: $5-10M
    • Dates: Jun-2016 - Oct-2017
    • Contact: Eric Wolfe, P.E.

    Full Description

    Swan Lake Reservoir Expansion

    Ketchikan, AK

  • Work Performed

    The Test Pile Program at the Port of Seattle’s Terminal 5 located along the Duwamish Waterway is in preparation of the […]


    • Location: Seattle, WA
    • Contract: < $3M
    • Dates: Jan-2016 - Mar-2016
    • Contact: Paul Powell Jr.

    Full Description

    Terminal 5 Test Pile Program

    Seattle, WA

  • Work Performed

    The Don Statter Harbor supports recreational and commercial vessel fleets in Auke Bay. The Master Plan envisioned reconfiguration and expansion […]


    • Location: Juneau, AK
    • Contract: < $3M
    • Dates: May-2012 - October-2013
    • Contact: Gary Gillette

    Full Description

    Statter Harbor Moorage Improvements

    Juneau, AK

  • Work Performed

    Installation of seasonally removable fenders and ladders for Nome bulkheads, replacing fendering systems damaged by ice along the East and South […]


    • Location: Nome, AK
    • Contract: < $3M
    • Dates: Aug-2013 - Feb-2015

    Full Description

    Fender, Ladder, and Harbor Lighting Foundation

    Nome, AK

  • Work Performed

    Involved removing and disposing 43,000 cy of contaminated soil. Soil had been contaminated through diesel, bunker oils, and spoils from […]


    • Location: Avery, ID
    • Contract: $5-10M
    • Dates: Mar-2013 - Sep-2013
    • Contact: Terry Cundy

    Full Description

    Avery Landing Cleanup

    Avery, ID

  • Work Performed

    Provided a 70-ton crane for the installation and removal of a super sack diversion dam. Using a clam bucket, excavated […]


    • Location: Port Angeles, WA
    • Contract: < $3M
    • Dates: Mar-2013 - Mar-2013
    • Client: Macnak Construction, LLC

    Full Description

    Corrections for Elwha Water Facility

    Port Angeles, WA

  • Work Performed

    Demolition and removing of existing floating docks and utilities and installation of new in kind. Portions of the existing electric […]


    • Location: Hydaburg, AK
    • Contract: < $3M
    • Dates: Jan-2013 - Jun-2013

    Full Description

    Hydaburg Small Boat Harbor Renovation

    Hydaburg, AK

  • Work Performed

    Secant excavation for the North and South secant shafts.


    • Location: Seattle, WA
    • Contract: < $3M
    • Dates: Jul-2015 - Dec-2015
    • Client: Stellar J Corporation
    • Contact: Jeff Walker

    Full Description

    Fremont Siphon Replacement and Odor Control Facility

    Seattle, WA

  • Work Performed

    Retrofitted 230-ft x 60-ft barge for floating extension to a cruise ship berth. Involved construction of new and retrofitted dolphins, […]


    • Location: Skagway, AK
    • Contract: $3-5M
    • Dates: Sep-2012 - May-2013
    • Contact: Ed Hanousek

    Full Description

    Railroad Dock Floating Dock

    Skagway, AK

  • Work Performed

    Replace timber trestle pile with new pile. Also included replacing the Slip 3 timber overpass walkway, asphalt paving, and other […]


    • Location: Seattle, WA
    • Contract: $638,424
    • Dates: Aug-2012 - Feb-2013
    • Contact: Barbara Olsen

    Full Description

    SR 519 Seattle Timber Trestle Preservation

    Seattle, WA

  • Work Performed

    Installed 321 18-in dia. or 24-in dia. augercast pile. Called for tension and compression load tests. Also installed 165 ea. […]


    • Location: Bellingham, WA
    • Contract: $2,418,000
    • Dates: Aug-2012 - Oct-2013
    • Client: Strider Construction Co., Inc.
    • Contact: James Gebhardt

    Full Description

    Post Point Waste Water Treatment Facility

    Bellingham, WA

  • Work Performed

    The Ammunition Pier Piling Replacement consisted of the demolition, removal and replacement of 24-in dia. hollow and 18-in dia. pre-stressed concrete […]


    • Location: Port Hadlock, WA
    • Contract: $1,206,850
    • Dates: Sep-2012 -
    • Client: Reyes Construction Inc
    • Contact: Gustavo Anaya

    Full Description

    Ammunition Pier Repair

    Port Hadlock, WA

  • Work Performed

    Project included demolition of existing structures at the North and Central Terminal including excavation of approximately 4,275 cy clean material […]


    • Location: Bellingham, WA
    • Contract: $3,599,000
    • Dates: Sep-2012 - Jul-2013
    • Contact: Susan French

    Full Description

    Terminal Bulkhead and Pier Repair

    Bellingham, WA

  • Work Performed

    Complete dock structure with crane rail supported on 88 driven and socketed piles. The replacement project is directly adjacent to […]


    • Location: Kodiak, AK
    • Contract: $29,663,000
    • Dates: Apr-2014 - Feb-2016
    • Contact: Lon White

    Full Description

    Kodiak Pier 3 Replacement

    Kodiak, AK

  • Work Performed

    Installation of 14 ea. 24-in dia. x 60-ft depth and 12 ea. 16-in dia. x 55-ft depth reinforced augercast pile.


    • Location: Tacoma, WA
    • Contract: $120,400
    • Dates: Jun-2014 - Jul-2014
    • Client: General Mechanical, Inc.
    • Contact: Stephen Hoover

    Full Description

    Oil Refinery Augercast Pile

    Tacoma, WA