Projects Archive

  • Work Performed

    Constructed a partially penetrating breakwater to deflect swells from Skagway’s Small Boat Harbor. Involved driving more than 100 steel piles […]


    • Location: Skagway, AK
    • Contract: $3,300,000
    • Dates: Aug-2009 - Jan-2010
    • Client: Municipality of Skagway
    • Contact: Todd Nottingham

    Full Description

    Boat Harbor Surge Control

    Skagway, AK

  • Work Performed

    Installed temporary sheet pile crane pads for Piers 1, 2 and 3, drove test piles for test pile program, drove […]


    • Location: Sand Point, ID
    • Contract: $7,500,000
    • Dates: Oct-2008 - May-2010
    • Client: Parsons Corporation / RCI
    • Contact: Chris Zeppernick

    Full Description

    US 95 Sand Point North & South (Sandcreek Byway)

    Sand Point, ID

  • Work Performed

    Constructed new 600MT ship haul out facility consisting of steel pipe piles, composite steel, concrete deck girders and concrete abutment. […]


    • Location: Kodiak, AK
    • Contract: $10,400,000
    • Dates: Jul-2008 - Sep-2009
    • Client: City of Kodiak
    • Contact: Lon White

    Full Description

    St. Herman Harbor Boat Lift Facility

    Kodiak, AK

  • Work Performed

    Superfund site. Built new barge loading and unloading facility. Involved sheet pile, upland and in-water pile driving, contaminated dredging, demolition […]


    • Location: Seattle, WA
    • Contract: $2,800,000
    • Dates: Dec-2009 - Apr-2010
    • Client: Port of Seattle
    • Contact: Jerry Dowd

    Full Description

    Terminal 115 Berth Modifications

    Seattle, WA

  • Work Performed

    Drove test piles including PDA testing and re-strikes, installation of precast piles, cut off piles and offload for storage of […]


    • Location: Olympia, WA
    • Contract: $475,000
    • Dates: May-2009 - Jul-2009
    • Client: Hoffman Construction Company
    • Contact: Brent Anderson

    Full Description

    Olympia City Hall

    Olympia, WA

  • Work Performed

    Maintenance dredged 9,700 CY of contaminated material along the port facility pier. The dredged sediment was then transported by rail […]


    • Location: Olympia, WA
    • Contract: < $3M
    • Dates: Jan-2009 - Mar-2009
    • Client: Port of Olympia
    • Contact: Rick Anderson

    Full Description

    Marine Terminal Berths 2 & 3 Interim Action Dredging

    Olympia, WA

  • Work Performed

    Installed OPEN CELL® bull rail, 4 heavy duty barge bollards, erection and commissioning of 4 ea. 130-ft high-mast light towers, […]


    • Location: Naknek, AK
    • Contract: $2,700,000
    • Dates: Jul-2010 - Mar-2010
    • Client: Bristol Bay Borough
    • Contact: Marvin Smith

    Full Description

    Naknek Port Improvements

    Naknek, AK

  • Work Performed

    In coordination with Ruskin Construction, PPM was contracted to perform substructure work to the construction of a 4,300-ft pile-supported water […]


    • Location: Everett, WA
    • Contract: $8,500,000
    • Dates: Feb-2008 - Mar-2010
    • Client: Tri-State Construction, Inc
    • Contact: Paul Clements

    Full Description

    Ebey Slough Trestle Installation

    Everett, WA

  • Work Performed

    Furnished and drove steel test pile, furnished ST piling, drove ST pile and furnished steel pile tip/shoe.


    • Location: Nalley Valley, WA
    • Contract: $639,000
    • Dates: Apr-2009 - May-2010
    • Client: Guy F. Atkinson Construction
    • Contact: Dave Doles

    Full Description

    I-5 / SR 16 Westbound Nalley Valley Interchange

    Nalley Valley, WA

  • Work Performed

    Installed 80-ft gangway and floatation billets. Installed gangway concrete abutment and approach slab and handrail.


    • Location: Everett, WA
    • Contract: $119,800
    • Dates: May-2009 - May-2010
    • Client: Grade, Inc
    • Contact: Kreg Oveson

    Full Description

    10th Street Marine Park Shore Projection

    Everett, WA

  • Work Performed

    Constructed 16-ft wide float sections with DF decking. Constructed 12-ft wide float sections with thru-flow DF decking. Drove test piles, […]


    • Location: Sammamish, WA
    • Contract: $468,000
    • Dates: Feb-2009 - Mar-2009
    • Client: Dept. of Parks and Recreation
    • Contact: Jack Seipel

    Full Description

    Pine Lake Park Phase II Dock Construction

    Sammamish, WA

  • Work Performed

    Marina restoration. Replaced the existing dilapidated Seabeck Marina, condemned in 2005, with a 200-slip marina along the downtown Seabeck waterfront. […]


    • Location: Seabeck, WA
    • Contract: $350,000
    • Dates: Mar-2010 - Apr-2010
    • Client: Olympic View Marina, LLC
    • Contact: Boyer Halvorsen

    Full Description

    Seabeck Marina

    Seabeck, WA

  • Work Performed

    Furnish and install 60 concrete test pile and 120 ea. 14-in dia. concrete production pile; approx 12,256 LF installed.


    • Location: Fife, WA
    • Contract: $955,000
    • Dates: Jul-2009 - Jun-2010
    • Client: Tri-State Construction, Inc
    • Contact: Paul Clement

    Full Description

    Port of Tacoma Rd to King County Line – HOV

    Fife, WA

  • Work Performed

    Pile driving at various locations within Snohomish County.


    • Location: Everett, WA
    • Contract: $104,000
    • Dates: Jul-2009 - Aug-2009
    • Client: Snohomish County Purchasing Division
    • Contact: Donald Wolfe

    Full Description

    Snohomish County Various Locations

    Everett, WA

  • Work Performed

    Dredged boat ramp area, southern outfall and northern outfall. Removed and offloaded pile. Dredged unsuitable sediments in the entrance channel […]


    • Location: Des Moines, WA
    • Contract: $430,000
    • Dates: Jan-2009 - Jan-2009
    • Client: City of Des Moines
    • Contact: Joe Dusenbury

    Full Description

    Des Moines Marina Maintenance Dredge

    Des Moines, WA

  • Work Performed

    Deconstruction of two derelict sunken dry docks in 25-ft of water. Dry docks were too sunken to be easily raised. […]


    • Location: Renton, WA
    • Contract: $1,900,000
    • Dates: Jul-2008 - Feb-2009
    • Client: Dept. of Natural Resources
    • Contact: Melissa Ferris

    Full Description

    Lake WA Dry Dock Removal

    Renton, WA

  • Work Performed

    Dock and foundation repairs. Installed 180 cf  of floatation under the existing moorage adjacent to the concrete barge.


    • Location: Seattle, WA
    • Dates: Jun-2008 - Jun-2008
    • Client: Ivar's Inc
    • Contact: Jim Seaver

    Full Description

    Pier 54-55

    Seattle, WA

  • Work Performed

    Emergency pile repair.


    • Location: Seattle, WA
    • Contract: $440,000
    • Dates: Oct-2008 - Oct-2008
    • Client: Martin Smith, Inc
    • Contact: Mark Astor

    Full Description

    Pier 55-56 Essential Pile Repair

    Seattle, WA

Request Services